Our EC unit is manufactured to order with lead times noramlly being 4-10 weeks. This can be reduced subject to pre-planning and early commitment from the hirer.


Installation [+1-2 weeks]

Delivery, sitting and connection of services to Plant, subject to readiness of Hirer's site and infrastructure.


Commissioning [+1-2 weeks]

Testing of Plant and training of Hirer's nominated employees, to handover to Evaluation phase


Once commissioned the hirer enters an evaluation period which includes collaborative testing, lasting up to 12 weeks.